Major Findings From the Homebush Bay Remediation Commission
This section of the report contains the Commission’s major findings. Click here to view the full report at the Commissions of Inquiry web site.
Development Proposal
- The Lednez site is highly contaminated by a wide range of highly toxic chemicals.
- The near-shore surface sediments in the northeastern portion of Homebush Bay are highly contaminated by dioxins and presently pose a significant risk of harm to human health and the environment.
- Remediation of both the Lednez site and the near-shore surface sediments in the northeastern position of Homebush Bay would in all probability allow the lifting of the EPA’s significant risk of harm classification for that area of the Bay.
- Remediations of the near-shore surface sediments in the northeastern portion of Homebush Bay is the minimum area of the Bay which should be remediated.
- In the circumstances the do nothing option is not appropriate and would severely limit the planned residential development of the Rhodes Peninsula.
Technology Robustness
- The indirect heated thermal desorption (IHTD) technology is a proven technology for remediating contaminated soils and sediments with varying physical characteristics containing a range of concentrations of numerous chlorinated and other chemicals.
- The IHTD technology has not treated soils and sediments with the same physical characteristics and range of concentrations of numerous chemical contaminants as are contained in the soils and sediments on the Lednez site and in Homebush Bay.
- A rigorous commissioning and proving protocol is required for the IHTD technology before it could be given consent for full scale operation.
- An average minimum removal efficiency for dioxins in soil treated by the IHTD plant should be 98.0 percent.
- Base catalysed decomposition (BCD) technology is a proven technology for a proportion of the liquid condensate generated by the IHTD plant.
- Plasma Arc technology is a proven technology for the proportion of the more highly chlorinated wastes not able to be viably treated by the BCD technology.
Public Health
- The data relating to contaminants on the site and in Homebush Bay is comprehensive and is of an acceptable quality for the purposes of the human health and ecological risk assessments.
- A program to assess
the significance of
chemicals not well characterised
and those highlighted
by the site auditors
should be implemented
in the early stages
of remedial works.
- The use of an individual
chemical risk criteria
of 3.5 x 10-6 is consistent
with recognised methodology
for health risk assessment.
- The use a combined
chemical risk criteria
of 1 x 10-5 for all
chemicals is consistent
with recognised methodology
for health risk assessment.
- The health risk assessments
for the proposed remediation
of the Lednez site and
part of the bed of Homebush
Bay adopted recognised
methodologies.
- The NHMRC recommended
average lifetime daily
exposure of 70pg TEQ/kg
bw/month for dioxins
is the appropriate ALDE
for health risk assessment
purposes in Australia.
- A background dioxin
exposure level for the
community of 1.4pg TEQ/kg
bw/d is a reasonably
conservative value for
health risk assessment
purposes.
- The soil acceptance
criteria adopted for
the Lednez site would
ensure public health
is protected over the
long-term.
- A restrictive covenant
is required for the
Lednez site to ensure
the more highly contaminated
soils placed at depth
are not disturbed in
the future.
- As the actual concentrations
of chemicals in the
replaced soils would
be below the soil acceptance
criteria calculated
for the health risk
assessment, the actual
concentrations should
be specified as the
soil acceptance criteria.
- The level of remediation
proposed for Homebush
Bay, provided the fishing
ban remains, would ensure
the health of the community
is protected.
- Provided best practice
management is used to
control and minimise
dust generation as well
as the IHTD plant and
pre-treatment building
stack emissions , the
likelihood of public
health risk criteria
for both cancer and
non-cancer effects being
exceeded at adjacent
residential properties
during the remediation
activities is minimal.
- Sampling and analysis
of the dioxin content
of off-site soils before
and during remediation
activities is required.
Noise Amenity
- Noise levels at existing
and future residential
locations in proximity
to the Lednez site and
Homebush Bay remediation
activities would significantly
exceed daytime noise
level amenity criteria.
- Noise levels at existing
and future residential
locations in proximity
to the Lednez site and
Homebush Bay remediation
activities would generally
comply with evening
and night-time noise
level amenity criteria.
- The upper levels
of the nearer proposed
residential developments
would be exposed to
the highest daytime
noise levels.
- The Applicant has
adopted all reasonable
and feasible noise mitigation
measures in the design
of its remediation proposals.
- Some existing residents
in Blaxland Road would
accept raised daytime
noise levels, generally
consistent with the
current noise environment.
- Existing residents
would generally prefer
the remediation of the
Lednez site and Homebush
Bay to be completed
in a shorter period,
rather than limiting
the earthmoving equipment
on the site to reduce
noise levels, but substantially
lengthening the life
of the remediation project.
- The Applicant must
consult and co-operate
with adjacent landowners
to ensure the amenity
of future residents
is protected to the
maximum extent reasonably
achievable.
Air Quality
- PM10 particulates
have been confirmed
as affecting the health
of people and increasing
concentrations have
corresponding increased
health effects.
- There are well proven
methods to control and
minimise dust and odour
generation during remediation
activities which must
be adopted by the Applicant.
- Despite the use of
best practice methods
the concentration of
PM10 dust particulates
in the Rhodes locality
and especially at closer
residential premises
could exceed the 24-hour
average concentration
guideline of 50µg/m3.
- Background dust would
contribute 40 to 90
percent of the dust
concentration at the
times the 24-hour average
PM10 guideline of 50µg/m3
is exceeded in the Rhodes
locality.
- Cessation of earthmoving
activities should occur
when the total PM10
particulate concentration
is likely to exceed
50µg/m3 at any
occupied residence in
the locality.
- Air emissions from
the IHTD, BCD and Plasma
Arc plants are relatively
minor but do add to
the cumulative impacts.
- Emissions from earthmoving
equipment would add
to cumulative impacts
but have not been taken
into account.
- Air emissions from
the pre-treatment building
have the potential for
public health effects
and must be monitored
as required by the EPA.
- Air quality should
be monitored at 4 locations
on the site boundary
as proposed by the Applicant.
- Air quality in the
IHTD stack should be
monitored as required
by the EPA.
- Odour levels on the
site boundaries should
be monitored.
- The Applicant must
reasonably comply with
predictions for point
source emissions and
ground level concentrations
as predicted in the
EIS and supplementary
documentation to provide
the highest level of
protection to the community.
Wastewater
- Some of the toxic
chemical substances
in the soil and groundwater
are prohibited from
discharge to the sewer
under current restrictions.
- Current technology
would not provide a
viable means for the
Applicant to reduce
the chemicals of concern
to below their limits
of detection.
- The quality of any
wastewater discharged
to Sydney Water’s
sewerage system must
be such to ensure that
the health of maintenance
workers is protected
and the beneficial use
of biosolids is not
compromised.
- DIPNR, the EPA and
Sydney Water have adopted
a co-operative approach
to resolving issues
associated with the
treatment and disposal
of wastewater from the
site.
- The Applicant should
conduct wastewater treatment
trials on contaminated
groundwater extracted
from the Lednez site.
- The Applicant must
continue to consult
with DIPNR, the EPA
and Sydney Water to
develop and implement
effective and innovative
wastewater treatment
and management measures.
Ecological
- The water quality
in Homebush Bay should
be monitored by the
Applicant during remediation
activities.
- The benthic recovery
in the remediated near-shore
area of Homebush Bay
should be monitored
over a period of 10
years by the NSW Maritime
Authority.
- The level of dioxin
in the tissue of fish
taken from Homebush
Bay should be monitored
following remediation
by the NSW Maritime Authority
and NSW Fisheries.
- The quality of groundwater
flowing to Homebush
Bay from the Lednez
site should be monitored
following remediation.
- The reconstructed
sea wall should be of
a biota-friendly design.
- Remediation of a
larger area of Homebush
Bay would have additional
benefits by further
reducing chemical contaminant
concentrations and would
result in lower dioxin
levels in the tissue
of fish taken from Homebush
Bay.
- Remediation of the
2 remaining contaminated
“hotspots”
in Homebush Bay could
pose significant environmental
issues which would need
to be assessed prior
to further consideration
of additional remediation
in the Bay.
Co-ordination of Environmental
Management
- The Applicant must
take the lead role in
co-ordinating environmental
management in the SREP
29 area.
- The Applicant should
develop and implement
a developer co-operation
action plan in consultation
with other developers
in the SREP 29 area.
- DIPNR/EPA should
fund a full-time environmental
officer to monitor the
environmental aspects
of all development within
the SREP29 area.
- DIPNR should establish
and chair a Rhodes Peninsula
Environmental Reference
Group to overview remediation
and development in the
SREP 29 area.
Community Consultation
- The Applicant should
fund a community liaison
group for the life of
the proposal.
- The Applicant should
fund independent technical
advice for the community
for the life of the
proposal.
- Operational and monitoring
information should be
made readily available
to the community by
the Applicant, including
through an internet
site.
- An all hours complaint
registration procedure
must be implemented
by the Applicant.
- The community, through
the community liaison
group, must be given
the opportunity to comment
on environmental management
plans prior to approval
of the plans.
Download the Commissioner's
Recommendations

Approx 130KB
Download the Commissioner's
letter to the Minister

Approx 25KB
If you do
not have a copy of Adobe
Acrobat, please use the
link below to visit the
Adobe site to download
the application.
Click here
to download a Portable
Document Format (.pdf)
Reader.